Segment 1 (East of Wood Lily Rd – City Limits):
This Week:
• Final grading for residential lots near Raymond and Bergamot intersections.
• Subdrain grouting on exposed intakes near Raymond and Bergamot intersections.
Two-Week Plan:
• Finish sidewalk paving between Wood Lily and Raymond intersections.
• Final grade acceptance and seeding operations.
• Material cleanup near Raymond intersection.
• Construction traffic will increase along the detour route, David Dr., Windsor Dr., and
Kingston Dr. during Segment 2 paving on September 13th. See Segment 2 Notice on city website (https://solon-iowa.com) for more information.
Segment 2 (East of Green Acres Dr. – Wood Lily Rd):
This Week:
• Segment 2 paving preparations: reinforcement placed, stringline erected, subbase trimming, and cold joint preparations at all intakes and intersections.
Two-Week Plan:
• Segment 2 paving will occur on September 13th. See Segment 2 Notice on city website
(https://solon-iowa.com) for more information.
• Segment 2 intersection and sidewalk paving will begin the week of September 19th.
• Topsoil Placement, final grading, and seeding operations after sidewalk paving is complete.
Segment 3 (East of Highway 1 – Green Acres Dr.):
This Week:
• No work was completed in the area.
Two-Week Plan:
• Water main excavations near bank driveway. This work will occur before Segment 3 is officially closed.
• Segment 3 construction begins in 2-3 weeks. Traffic control/detour maps will be updated 1-week prior to Segment 3 closure.
Traffic Control:
Traffic should continue using the established detour route. Traffic
control/detour adjustments anticipated for September 26th. Updates will be provided one week in advance.