Segment 1 (East of Wood Lily Rd – City Limits)
This Week:
• Saddleback Contractor fixed water valve issues east of Bergamot Ln.
Two-Week Plan:
• Finish sidewalk paving up to Wood Lily intersection after Segment 2 roadway paving.
• Hydrant extension east of Bergamot intersection.
• Segment 2 paving will occur between August 31st – September 6th. Construction traffic will increase along the detour route, David Dr., Windsor Dr., and Kingston Dr. during paving.
Segment 2 (East of Green Acres Dr. – Wood Lily Rd)
This Week:
• Subgrade and base improvements between Green Acres and Windsor intersections.
• Subdrains installed and connected to intakes west of Kingston Dr.
• Poured new intakes and storm sewer east of Green Acres Dr.
• Gas main conflict and relocation by utility companies.
• Filter socks and drainage grading between Green Acres and Kingston.
Two-Week Plan:
• Subgrade preparations west of Kingston intersection.
• Intake and storm sewer removal at care center.
• Install subdrains between Green Acres and Kingston intersections.
• Segment 2 roadway paving begins around August 31st – September 6th. Segment 2 roadway will be open 1-2 weeks after paving is completed.
Segment 3 (East of Highway 1 – Green Acres Dr.)
This Week:
• Sidewalk removal at Green Acres NE Sidewalk.
Two-Week Plan:
• Segment 3 construction will begin in approximately 2-3 weeks. Traffic control/detours will be updated prior to Segment 3 closure.
Traffic Control
Traffic should continue using the established detour route. Updates will be provided one week in advance.