Segment 1 (East of Wood Lily Rd – City Limits):
This Week:
• Subgrade prepared for remainder of Segment 1 paving.
Two-Week Plan:
• Grading near sidewalks along Segment 1. Finish sidewalk paving up to Wood Lily intersection after Segment 2 roadway paving.
• Segment 2 paving will occur between August 25th – August 30th. Construction traffic will increase along the detour route, David Dr., Windsor Dr., and Kingston Dr. during paving.
Segment 2 (East of Green Acres Dr. – Wood Lily Rd):
This Week:
• Subgrade and base improvements between Kingston and David intersections.
• Subdrains installed and connected to intakes east of Kingston Dr.
• Sidewalk removal and future sidewalk grading east of Green Acres Dr.
• Side street pavements and driveways removed for all of Segment 2.
• Removal of existing intakes and storm sewer west of Windsor intersection.
• Power pole adjustments and relocation by utility companies.
Two-Week Plan:
• Subgrade preparations at Kingston intersection.
• Install intakes east of Green Acres intersection.
• Install subdrains between Green Acres and Windsor intersections.
• Segment 2 roadway paving to occur between August 25th – August 30th. Segment 2
roadway will be open 1-2 weeks after paving is completed.
Segment 3 (East of Highway 1 – Green Acres Dr.)
This Week:
• No work was completed in this area.
Two-Week Plan:
• Segment 3 construction will begin in approximately 2-3 weeks. Traffic control/detours will be updated prior to Segment 3 closure.
Traffic Control:
Traffic should continue using the established detour route. See the map for detour routes and roadway closures. Updates will be provided one week in advance.