Segment 1 (East of Wood Lily Rd – City Limits):
This Week:
• Grading near Wood Lily, Bergamot, and the Saddleback subdivision.
• Stockpile preparations for Segment 2 paving completed near Raymond intersection.
Two-Week Plan:
• Grading near sidewalks along Segment 1. Finish sidewalk paving up to Wood Lily intersection after Segment 2 roadway paving.
• Segment 2 paving will occur within the next two weeks. Construction traffic will increase along the detour route and Raymond intersection.
Segment 2 (East of Green Acres Dr. – Wood Lily Rd):
This Week:
• Road Core-outs and subgrade improvements east of David intersection.
• Subdrains installed and connected to intakes near preservation area.
• Grading for north sidewalk east of Windsor Dr.
• All segment 2 intakes connections and bases have been sealed with concrete.
• Side street pavement removed at Wood Lily intersection.
• Subgrade improvements at Wood Lily intersection.
Two-Week Plan:
• Sidewalk grading and subgrade preparations along north side of Segment 2.
• Install subdrains and connect to intake structures.
• Utility relocations of power poles and communication junction boxes.
• Segment 2 roadway paving to occur in approximately 2 weeks. Updates to traffic control will be provided prior to changes.
Segment 3 (East of Highway 1 – Green Acres Dr.)
This Week:
• No work was completed in this area.
Two-Week Plan:
• Utility relocations to prepare for construction in Segment 3.
Traffic Control:
Traffic should continue using the established detour route. See the attached map for detour routes and roadway closures. Updates will be provided one week in advance.