Segment 1 (East of Wood Lily Rd – City Limits):
This Week:
• Grading was completed near Raymond and Bergamot intersections.
Two‐Week Plan:
• Grading east of Wood Lily Rd, Sidewalk paving once grade and base are prepared.
• Contractor will place erosion stone at the storm sewer outlet near the golf course.
• Saddleback Estates Subdivision will be paving internal roadways.
Construction vehicle traffic will increase along detour during this time.
Segment 2 (East of Green Acres Dr. – Wood Lily Rd):
This Week:
• 5th Street pavement removed using milling machine.
• Subdrains installed and connected to intakes north of Wood Lily intersection.
• All storm crossings were completed. Several intake structures were poured.
• Sidewalk grading east of David Dr., sidewalk near Wood Lily intersection was removed.
Two‐Week Plan:
• Finish pouring intake structures near Windsor and David intersections.
• Sidewalk grading and subbase preparations along north side of Segment 2.
• Install subdrains and connect to intake structures.
• Utility relocations between Windsor and David Intersections.
• Segment 2 roadway paving to occur in 2‐3 weeks. Updates on traffic control will be provided prior to changes.
Segment 3 (East of Highway 1 – Green Acres Dr.)
This Week:
• Roadway removed; curb fillets rolled for access along Segment 3.
• Utility relocations north of the Bridge Community Bank.
Two‐Week Plan:
• Exploratory excavation will occur east of the Bank’s access to 5th Street. Engineers and City staff will evaluate the condition of water main and make improvements as needed.
• Utility relocations will occur to prepare for construction in Segment 3.
Traffic Control:
Traffic should continue using the established detour route. Updates will be provided one week in advance.