Segment 1 (East of Wood Lily Rd – City Limits)
This Week:
• Sidewalk was paved east of Raymond Dr. and South of 5th Street.
• Underground utility coordination and installation.
Two‐Week Plan:
• Grading east of Wood Lily Rd, Sidewalk paving once grade and base are prepared.
• Contractor will place erosion stone at the storm sewer outlet near the golf course.
• Saddleback Estates Subdivision will be paving internal roadways in early August.
Construction vehicle traffic will increase along detour during this time.
Segment 2 (East of Green Acres Dr. – Wood Lily Rd)
This Week:
• Water main was connected at David Dr.
• Mainline storm sewer for segment 2 was completed.
• Excavation for north sidewalk continued to Windsor Dr.
Two‐Week Plan:
• Storm sewer crossings and intake structures completed for segment 2.
• Roadway removal was scheduled to begin Monday, August 1st. Removals will extend through
Segment 3.
Segment 3 (East of Highway 1 – Green Acres Dr.)
This Week:
• No work was completed in this area.
Two‐Week Plan:
• Exploratory excavation will occur east of the Bank’s access to 5th Street. Engineers and
City staff will evaluate the condition of water main and make improvements as needed.
• Roadway removal was to begin Monday, August 1st.
Traffic Control:
Traffic should continue using the established detour route. See the attached
map for detour routes and roadway closures. Updates will be provided one week in advance.